5 August 2026
Cue Hub Expansion to 1.7Mtpa in FY28
Cue mine outputs lifting in FY27 deliver increased ore optionality and
FY28 gold output
Perth, Western Australia, 5 August 2026: Westgold Resources Limited (ASX | TSX: WGX,
Westgold or the Company) is pleased to announce its commitment to the Cue Expansion Plan
(CXP), a capital-light expansion of the Company’s Cue processing hub from its current 1.4Mtpa
run rate to 1.7Mtpa in FY28.
This plan reflects a deliberate shift towards processing hub optimisation across the wider
business. The CXP is underpinned by increasing underground mine outputs from Westgold’s Big
Bell and Great Fingall mines near Cue.
Further upside may come from other ore sources currently in production including the operating
Fender underground (≈0.2Mtpa) and smaller open pits near Cue. There is also potential for third-
party ore supply via existing ore purchase agreements and if drilling is successful, from Westgold
brownfields open pit resource targets at Big Bell South and Cuddingwarra.
CXP – 1.4Mtpa throughput to 1.7Mtpa in FY28
The CXP is a capital-light pathway to increase Cue processing hub throughput from 1.4Mtpa to
1.7Mtpa in FY28 by debottlenecking the existing circuit. Study work indicates increasing the mill
motor power from 2.9MW to 4.2MW through a replacement liquid-cooled motor and variable speed
drive, together with associated system and pumping upgrades will support operation at the higher
duty.
The process plant upgrade is designed to increase the milling circuit throughput from the current
nominal 170 t/h to 200 t/h. This expansion is scheduled to be complete in late FY27, with the higher
installed capacity supporting an increase of approximately 15kozpa from the Cue hub from FY28
onwards.
Westgold will now progress detailed engineering, procurement planning and execution
sequencing for the CXP while continuing brownfields drilling at near-mill opportunities to define
future ore optionality.
Cue Hub Expansion to 1.7Mtpa in FY28
5 August 2026
2
Westgold Managing Director and CEO Wayne Bramwell commented:
“Bigger mines need bigger mills. Westgold’s underground mine outputs are growing across all the
Murchison operations and building ore stockpiles from FY27 onwards.
In addition, open pit mining is now underway at Cue and Meekatharra, with this organic growth
underpinning the incremental expansion of our Cue business. This simple upgrade and modest
capital investment at the Cue hub reflects a deliberate shift towards processing hub optimisation
and expansion, with lower operating costs and higher cashflow the objective.
At Cue, small open pits are being developed now and additional near-hub open pit resource
development opportunities at Big Bell South and Cuddingwarra exist. These targets are larger, are
within approximately 50km of our Cue hub and if drilling is successful, can add significant
additional ore sources in FY28.”
Highlights
CXP sees Cue hub throughput increase from 1.4Mtpa to 1.7Mtpa
~21% increase in Cue processing capacity by FY28
Baseline production uplift – CXP adds ≈ 15kozpa to Cue once commissioned
Supported by increasing outputs from Big Bell and Great Fingall underground mines and
new regional open pits currently operating
Brownfields resource definition drilling and open pit optimisations commenced
Big Bell South and Cuddingwarra (near Cue) drilling has begun
Key CXP Scoping Study outputs include:
Indicative capital of $22M – commissioning in FY27
Payback period of 10 months
Life of Mine (LoM) gold production 1.1 – 1.3 Moz
at All in Sustaining Cost (AISC) range of $2,916 - $3,564/oz
NPV of Cue improves by ~$400M at a gold price of $5,500/oz
Cue Hub Expansion to 1.7Mtpa in FY28
5 August 2026
3
Cautionary Statement
The Scoping Study referred to in this report is based on low-level technical and economic
assessments and is insufficient to support estimation of Ore Reserves or to provide assurance of
an economic development case at this stage, or to provide certainty that the conclusions of the
Scoping Study will be realised. The information in this announcement relating to processing
expansion concepts, study outcomes, resource definition work, potential brownfields
opportunities and indicative financial metrics is based on preliminary internal and consultant
study work.
The CXP study is at scoping-study level and associated capital estimates are described as having
estimate accuracy of ±35%. The expansion studies are also preliminary in nature.
The financial metrics presented in this announcement are indicative study-stage ranges only, are
provided to illustrate the potential scale of the opportunities under internal development
scenarios and should not be interpreted as a Final Investment Decision or an Ore Reserve
statement. Any future public reporting of Mineral Resources, Ore Reserves, production targets or
forecast financial information will be made in accordance with the ASX Listing Rules and the JORC
Code (2012), where applicable.
The production target is predominantly sourced from Ore Reserves and Inferred Mineral
Resources. There is a low level of geological confidence associated with Inferred Mineral
Resources, and there is no certainty that further exploration work will result in the determination
of Indicated Mineral Resources for the current Inferred portion, or that the production target itself
will be realised.
A minor portion of the production target during FY32-FY33 is sourced from the Big Bell South
Exploration Target. The Exploration Target is conceptual in nature and there has been insufficient
exploration to estimate a Mineral Resource. It is uncertain if further exploration will result in the
estimation of a Mineral Resource. The Company believes there is a reasonable basis for the
inclusion of the Exploration Target given its limited contribution to the overall production target
and the supporting geological evidence.
The Scoping Study referred to in this announcement has been undertaken to evaluate the
potential expansion of the Cue processing facility. It is a preliminary technical and economic
study of the potential viability of increasing throughput at Westgold’s Cue hub, based on low level
technical and economic assessments that are not sufficient to support the estimation of Ore
Reserves. Further evaluation work and appropriate studies are required before Westgold will be
in a position to estimate any Ore Reserves or to provide any assurance of an economic
development case.
The Scoping Study is based on the material assumptions outlined below. These include
assumptions about the availability of funding. While Westgold considers all of the material
assumptions to be based on reasonable grounds, there is no certainty that they will prove to be
correct or that the range of outcomes indicated by the Scoping Study will be achieved.
Cue Hub Expansion to 1.7Mtpa in FY28
5 August 2026
4
The forecast capital payback period of approximately 10 months occurs prior to the scheduled
extraction of the majority of Inferred Mineral Resources and before any reliance on the Big Bell
South Exploration Target. As a result, recovery of the expansion capital is supported
predominantly by Ore Reserves and existing operating inventory. Westgold believes that it has a
reasonable basis for providing these forward-looking statements and the forecast financial
information based on material assumptions outlined in this release.
While Westgold considers all the material assumptions used in the Scoping Study to be based on
reasonable grounds, there is no certainty that they will prove to be correct or that the range of
outcomes indicated by the Scoping Study will be achieved.
Mining areas within the production target are fully permitted and available for ongoing resource
definition and eventual mining. To achieve the range of outcomes indicated in the Scoping Study,
funding in the order of $22M will likely be required. The Company as at 30 June 2026 had $939M
of cash, bullion and liquid investments (refer ASX – 22 July 2026, June 2026 Quarterly Report).
Additionally, Westgold announced it had executed a commitment letter with its existing lenders
to increase its Syndicated Facility Agreement to $600M which remained undrawn as at the date of
this announcement.
Given the uncertainties involved, investors should not make any investment decisions based
solely on the results of the Scoping Study.
Readers should not assume that the brownfields opportunities described at Big Bell South will
necessarily be converted into future Ore Reserves for the expanded processing hubs.
Advancement of any of these opportunities remains subject to drilling results, geological
interpretation, mine design, mine planning, technical and commercial studies, approvals,
stakeholder engagement and all applicable regulatory and disclosure requirements.
Cue Hub Expansion to 1.7Mtpa in FY28
5 August 2026
5
1.0 Cue Expansion Project (CXP) – 1.4Mtpa to 1.7Mtpa in FY28
Westgold’s Murchison expansion strategy reflects a deliberate shift towards processing hub
optimisation from FY27 onwards, using established infrastructure to convert increasing
mine outputs into higher throughput and cash generation.
Rather than treating each ore source or processing opportunity in isolation, Westgold is pursuing
regional development logic to maximise throughput, lower costs and lift free cash flow from
established infrastructure across the Murchison operating footprint (Figure 1).
Figure 1: Cue and Meekatharra Hubs
Cue Hub Expansion to 1.7Mtpa in FY28
5 August 2026
6
This approach materially improves capital productivity by leveraging existing infrastructure,
reducing haulage costs, shortening execution pathways and positioning the business to convert
production growth into cash generation at a lower marginal capital cost than a greenfields
solution.
This strategy is also aligned with Westgold’s broader self-funded growth model.
In practical terms, the ability to pursue growth through brownfields infrastructure upgrades
provides a lower-risk pathway to accelerate production, lower processing unit costs and increase
free cash flow without relying on external financing or long development timelines.
At the Cue processing hub, the preferred expansion pathway targets debottlenecking of the
existing circuit (Figure 2).
Existing study work indicates that the core constraint to materially increasing throughput at the
plant is installed mill power. The selected concept therefore focuses on increasing mill motor
power from 2.9MW to 4.2MW through a replacement liquid-cooled motor and variable speed drive,
together with associated system upgrades to support operation at the higher duty.
The process plant upgrade is designed to increase the milling circuit throughput from the
current nominal 170 t/h to 200 t/h by:
Replacing the 2.9MW mill motor with a 4.2MW motor;
Reconfiguring the internal mill lining to accommodate a grate wall discharge system;
Replacing the gearbox pinions, drive pinion and ring gear with a higher specification alloy;
Replacing the carbon safety screen with a larger screen;
Replacing the cyclone feed pumps;
Upgrading the plant and booster tailings pumps;
Upgrading the process water pumps; and
Upgrading the power distribution networks and hardware to accommodate the higher
power draw.
Cue Hub Expansion to 1.7Mtpa in FY28
5 August 2026
7
Figure 2: Cue Processing Hub
By increasing available power and improving driveline control through a variable speed drive, Cue
can operate at a higher sustained throughput target of approximately 1.7Mtpa. The use of an
interchangeable motor and retrofitting the existing switch room lowers civil and structural
disruption, reduces schedule risk and installation complexity, and improves overall capital
efficiency.
The CXP takes advantage of the increased ore supply provided by growing production at Big Bell
and the ramp-up at Great Fingall. The upgrade is expected to require only limited downtime for
tie-in, allowing Westgold to increase throughput with a modest capital requirement and lower
execution risk than a new plant build.
CXP Scoping Study Summary
Note that all Scoping Study values represented are mid-point. Ranges are provided in Table 2.
Average annual gold production of approximately 122koz (an increase of 15koz) - for
total gold production of 1.2Moz over 10 years (an increase of 134koz)
Processing underpinned by the long-life (>16 years) Big Bell underground mine - with
supplementary high-grade feed from the historic Great Fingall mine
Scoping study assumes an upgrade of the current Cue 1.4Mtpa plant to 1.7Mtpa - for a
capital cost of $22M (upper range)
Life of mine AISC of approximately $3,240/oz
Pre-tax undiscounted cashflow of approximately $1.7B - at a gold price of $5,500/oz
increasing to $2.3B at Spot Gold Price ($6,000/oz)
NPV of approximately $1.1B - at a gold price of $5,500/oz.
Cue Hub Expansion to 1.7Mtpa in FY28
5 August 2026
8
An indicative comparison between the midpoints of the CXP and current operating plan (without
CXP case) is shown below in Table 1 (gold price $5,500/oz). This highlights the substantially
improved economics and processing capability within the region at only a slight reduction in
grade.
Metric Units Current CXP
Mined Tonnes kt 14,552 16,537
Mined Grade g/t 2.52 2.49
Mined Ounces koz 1,180 1,323
Recovered Ounces koz 1,081 1,198
Free Cashflow $M 1,121 1,729
NPV $M 674 1,075
Table 1: CXP comparison against current mine plan
Preliminary Financial Overview
The key physical and financial metrics in Table 2 and 3 below are presented as indicative study-
stage ranges reflecting the preliminary nature of the current work, including scoping-level
estimate accuracy, study assumptions and internal scenario sensitivity. They are shown to
illustrate the potential scale of value creation from the expansion pathway and should not be
interpreted as a Final Investment Decision.
The production targets outlined in Table 2 below are at a Scoping Study level and should be read
together with the cautionary statements in this announcement.
Table 2: Key Physical Assumptions
Metric Units Outputs
Life of Mine Years 10
Installed Throughput Mtpa 1.7
Material Mined Mt 15 – 18
Mined Grade g/t 2.2 – 2.7
Mined Ounces Moz 1.2 – 1.5
Material Processed Mt 15 – 18
Payable Metal (post recovery) Moz 1.1 – 1.3
Cue Hub Expansion to 1.7Mtpa in FY28
5 August 2026
9
A gold price of $5,500/oz has been used to assess the indicative economics of the CXP, which
is forecast to generate an unleveraged NPV of approximately $1.1B.
Table 3: Financial Results Summary
Financials at 7.3% Discount Factor Units Output
Gold Price $/oz 5,500
Project Free Cash flow pre-tax $B 1.6 – 1.9
Project NPV $B 1.0 – 1.2
AISC $/oz 2,916 – 3,564
Sensitivity Analysis
Figure 3 depicts sensitivity analysis for CXP. It shows that while sensitive to gold price, the
project NPVs are resilient to both discount rate and cost.
Figure 3: CXP Sensitivity Analysis
600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600
Discount Rate (±10%)
Capital Costs (±10%)
Op Cost (±10%)
Gold Price (±10%)
NPV ($'M)
CXP Sensitivity Analysis
Cue Hub Expansion to 1.7Mtpa in FY28
5 August 2026
10
CXP Basis for Production Target
The Production Target for CXP is underpinned predominantly by a combination of Ore Reserves at
Big Bell and Great Fingall, together with Inferred Mineral Resources at Great Fingall (Figure 4).
The production schedule shows a temporary dip in FY32 from Big Bell. This reflects conservative
development rates assumed in the Big Bell Deeps life of mine plan, which are designed to
establish the number of production fronts required to sustain full production rates. Westgold
expects the Cue hub to have several potential ore sources that could help offset this dip and
support utilisation of the expanded mill.
These include:
Big Bell South and the broader Big Bell trend – priority near-mine targets currently the
subject of substantial resource definition drilling (Figure 5);
Cuddingwarra – an additional brownfields opportunity near Cue, also being assessed as part
of Westgold’s resource definition and optimisation program;
regional low-grade surface stockpiles – approximately 3.8Mt at 0.7g/t, available for reclaim
and processing, providing a flexible source of supplementary feed; and
existing ore purchase agreements – which may provide further third-party ore feed into the
expanded Cue processing hub.
The Big Bell South Exploration Target and identified mining stockpiles (mined material in excess
of milling capacity in FY27) have been included within the production target. Other opportunities
including Cuddingwarra, low-grade surface stockpiles and third-party ore have not been included
in the physical or financial assessment.
Figure 4: Production Schedule – CXP
0
500
1,000
1,500
2,000
2,500
3,000
FY27 FY28 FY29 FY30 FY31 FY32 FY33 FY34 FY35 FY36
MIned/Processed
(ktpa)
Big Bell Reserve Great Fingall Reserve
Great Fingall Inferred Big Bell South Exploration Target
Mining Stockpile Processing Capacity
Cue Hub Expansion to 1.7Mtpa in FY28
5 August 2026
11
CXP Capital Costs
The CXP capital cost estimate in Table 4 is derived based on mechanical equipment lists from
several sources such as quotes, and actual prices used from Westgold’s current operating
mines. The study-level capital estimate for CXP has been determined at approximately $14M-
$22M.
Whilst overall contingency has been determined as a single line-item related to the total cost,
additional contingency has been built into the individual cost estimates reflecting the high-level
scoping nature of the study.
Table 4: Capital Cost Estimate – CXP
Equipment Name Units Cost
Milling $M 5.9 – 9.0
Cyclones $M 0.2 – 0.3
Leach and Adsorption $M 0.4 – 0.6
Water Supply $M 0.5 – 0.7
Power Distribution $M 1.8 – 2.7
Total Equipment $M 8.6 – 13.3
Direct Costs $M 3.2 – 4.9
Indirect Costs $M 0.7 – 1.1
Contingency $M 1.8 – 2.7
Total Costs $M 14.4 – 22.1
Risks, Study Maturity and Mitigation Pathway
As with any processing expansion at this maturity, it remains subject to the risks and
uncertainties typical of study-stage brownfields developments.
For CXP, the key execution sensitivities relate to timely procurement of long lead electrical and
mechanical components, outage planning, installation sequencing and commissioning reliability
once the upgraded drive system is introduced.
The mill motor has been ordered and delivery is scheduled in Q4, FY27.
Cue Hub Expansion to 1.7Mtpa in FY28
5 August 2026
12
2.0 Murchison Brownfields Resource Definition Opportunities
Westgold’s portfolio review identified and ranked multiple mature assets within the Murchison
that could deliver incremental open pit ore sources into existing regional operating centres. With
disciplined capital allocation these opportunities can be progressively tested through resource
definition, mine design and economic evaluation across the three-year outlook (3YO).
These opportunities are all located within the broader Murchison operating footprint and sit
within short haulage distance of Westgold’s Cue and Meekatharra processing hubs. Each area
also benefits from historical mining activity, existing or legacy infrastructure and established
geological knowledge, making them attractive brownfields targets for further evaluation.
One such opportunity identified was Big Bell South, and the resource definition and open pit
optimisation work underway could deliver improved CXP outcomes. Big Bell South (Figure 5) is
being assessed as a potential open pit extension of the wider Big Bell mineralised trend.
Figure 5: Big Bell Trend Long Section
Drilling of the Big Bell South trend from surface has begun with multiple rigs located at 1600
and Shocker drilling the potential extensions.
This will encompass Stage One of drilling at Big Bell South which will be ongoing throughout the
first half of FY27, with Stage Two toward the end of FY27. It is expected an initial Scoping Study
will be completed at the conclusion of Stage One.
This brownfields work is especially relevant because it strengthens the strategic rationale for
higher installed processing capacity at Cue.
Cue Hub Expansion to 1.7Mtpa in FY28
5 August 2026
13
Further portfolio analysis across Cue is ongoing, with additional opportunities around the historic
Cuddingwarra trend (Figure 1) being assessed for potential future advancement. If the current
drilling and optimisation programs are successful, they have potential to supplement
underground feed sources, improve ore blend management and support sustained high
utilisation across the expanded mills.
3.0 Next Steps
Organic growth from Westgold’s existing Cue mines and the proposed brownfields resource
definition program outline a regional growth strategy for Westgold’s Cue operations with multiple
advantages.
The CXP is underpinned by this organic growth and:
materially lifts installed processing capacity at the Cue hub to 1.7Mtpa by FY28;
utilises the expansion of existing infrastructure, which is lower risk and more capital efficient
relative to a new plant build;
creates an incremental, lower-risk and near-term pathway to higher gold production, lower
processing unit costs and enhanced free cash flow - leveraging assets Westgold already
owns and operates; and
provides management with a broader suite of future ore-source options to improve regional
scheduling flexibility, plant utilisation and cash flow generation.
The next phases of work are expected to include additional engineering definition, sundry
procurement planning, vendor engagement and more detailed execution sequencing so that
shutdowns can be managed efficiently and long lead items can be secured where appropriate.
In parallel, Westgold will continue to advance the brownfields resource definition work so that
future ore optionality can be assessed against haulage, mine design, processing fit and capital
intensity.
This announcement is authorised for release to the ASX by the Board.
Investor and media relations enquiries
Investor Relations
KasunLiyanaarachchi
Group Manager Investor Relations & Communications
investor.relations@westgold.com.au
+61 458 564 483
Media
Annette Ellis
Manager Communications & Corporate Affairs
Media@westgold.com.au
+61 458 200 039
Cue Hub Expansion to 1.7Mtpa in FY28
5 August 2026
14
Compliance Statements
Competent/Qualified Person Statements
Exploration Results and Mineral Resources Estimates
The information in this release that relates to Exploration results and Mineral Resource Estimates
is compiled by Westgold technical employees and contractors under the supervision of Mr. Jake
Russell B.Sc. (Hons), who is a member of the Australian Institute of Geoscientists and who has
verified, reviewed and approved such information. Mr Russell is a full-time employee of the
Company and has sufficient experience which is relevant to the styles of mineralisation and types
of deposit under consideration and to the activities which he is undertaking to qualify as a
Competent Person as defined in the 2012 Edition of the Australasian Code for Reporting of
Exploration Results, Mineral Resources and Ore Reserves (the “JORC Code”) and as a Qualified
Person as defined in the CIM Guidelines and National Instrument 43-101 – Standards of
Disclosure for Mineral Projects (“NI 43-101”). Mr. Russell is an employee of the Company and,
accordingly, is not independent for purposes of NI 43-101. Mr Russell consents to and approves
the inclusion in this release of the matters based on his information in the form and context in
which it appears. Mr Russell is eligible to participate in short- and long-term incentive plans of the
company.
Ore Reserves
The information in this release that relates to Ore Reserve is based on information compiled by
Mr. Leigh Devlin B.Eng. FAusIMM, who has verified, reviewed and approved such information. Mr.
Devlin has sufficient experience which is relevant to the styles of mineralisation and types of
deposit under consideration and to the activities which they are undertaking to qualify as a
Competent Person as defined in the JORC Code and as a Qualified Person as defined in the CIM
Guidelines and NI 43-101. Mr. Devlin is an employee of the Company and, accordingly, is not
independent for purposes of NI 43-101. Mr. Devlin consents to and approves the inclusion in this
release of the matters based on his information in the form and context in which it appears. Mr.
Devlin is a full-time senior executive of the Company and is eligible to and may participate in
short-term and long-term incentive plans of the Company as disclosed in its annual reports and
disclosure documents.
General
Mineral Resources, Ore Reserve Estimates and Exploration Targets and Results are calculated in
accordance with the JORC Code. Investors outside Australia should note that while Ore Reserve
and Mineral Resource estimates of the Company in this announcement comply with the JORC
Code (such JORC Code-compliant Ore Reserves and Mineral Resources being "Ore Reserves"
and "Mineral Resources" respectively), they may not comply with the relevant guidelines in other
countries. The JORC Code is an acceptable foreign code under NI 43-101. Information contained
in this release describing mineral deposits may not be comparable to similar information made
public by companies subject to the reporting and disclosure requirements of US securities laws,
including Item 1300 of Regulation S-K. All technical and scientific information in this release has
been prepared in accordance with the Canadian regulatory requirements set out in NI 43-101 and
has been reviewed on behalf of the Company by Qualified Persons, as set forth above.
Cue Hub Expansion to 1.7Mtpa in FY28
5 August 2026
15
This release contains references to estimates of Mineral Resources and Ore Reserves. The
estimation of Mineral Resources is inherently uncertain and involves subjective judgments about
many relevant factors. Mineral Resources that are not Ore Reserves do not have demonstrated
economic viability. The accuracy of any such estimates is a function of the quantity and quality of
available data, and of the assumptions made and judgments used in engineering and geological
interpretation, which may prove to be unreliable and depend, to a certain extent, upon the
analysis of drilling results and statistical inferences that may ultimately prove to be inaccurate.
Mineral Resource estimates may require re-estimation based on, among other things: (i)
fluctuations in the price of gold; (ii) results of drilling; (iii) results of metallurgical testing, process
and other studies; (iv) changes to proposed mine plans; (v) the evaluation of mine plans
subsequent to the date of any estimates; and (vi) the possible failure to receive required permits,
approvals and licenses.
Forward Looking Statements
These materials prepared by Westgold Resources Limited include forward looking statements.
Often, but not always, forward looking statements can generally be identified by the use of
forward looking words such as “may”, “will”, “expect”, “intend”, “believe”, “forecast”, “predict”,
“plan”, “estimate”, “anticipate”, “continue”, and “guidance”, or other similar words and may
include, without limitation, statements regarding the Company’s 3YO, including estimates of
gold production, grades, recoveries and its expectations regarding AISC, the timing of updates to
Mineral Resource estimates or Ore Reserves, plans, strategies and objectives of management,
anticipated production or construction commencement dates and expected costs or production
outputs.
Forward looking statements inherently involve known and unknown risks, uncertainties and other
factors that may cause the Company’s actual results, performance and achievements to differ
materially from any future results, performance or achievements. Relevant factors may include,
but are not limited to, changes in commodity prices, foreign exchange fluctuations and general
economic conditions, increased costs and demand for production inputs, the speculative nature
of exploration and project development, including the risks of obtaining necessary licenses and
permits and diminishing quantities or grades of reserves, political and social risks, changes to the
regulatory framework within which the Company operates or may in the future operate,
environmental conditions including extreme weather conditions, recruitment and retention of
personnel, industrial relations issues and litigation.
Forward looking statements are based on the Company’s and its management’s good faith
assumptions relating to the financial, market, regulatory and other relevant environments that
will exist and affect the Company’s business and operations in the future. The Company does not
give any assurance that the assumptions on which forward looking statements are based will
prove to be correct, or that the Company’s business or operations will not be affected in any
material manner by these or other factors not foreseen or foreseeable by the Company or
management or beyond the Company’s control.
Cue Hub Expansion to 1.7Mtpa in FY28
5 August 2026
16
Although the Company attempts and has attempted to identify factors that would cause actual
actions, events or results to differ materially from those disclosed in forward looking statements,
there may be other factors that could cause actual results, performance, achievements or events
not to be as anticipated, estimated or intended, and many events are beyond the reasonable
control of the Company. In addition, the Company’s actual results could differ materially from
those anticipated in these forward looking statements as a result of the factors outline