Westgold Declares Maiden South Junction Ore Reserve- Updated
Released
Released
Announcement PDF
ASX Announcement
16 August 2024
Westgold Declares Maiden South Junction Ore Reserve - Updated
Bluebird-South Junction expands to 1.2Mtpa run rate from Q3 FY25
Westgold Resources Limited (ASX: WGX, TSX: WGX, OTCQX: WGXRF – Westgold or the
Company) is pleased to present the maiden Ore Reserve for its South Junction mine. South
Junction is a part of a broader Bluebird - South Junction mining complex which is becoming the
primary ore source for the Bluebird processing hub at Meekatharra with a 1.2Mtpa run rate
targeted from Q3, FY25.
Highlights
Bluebird – South Junction Ore Reserve increases to 3.0Mt @ 2.8g/t Au for 277koz
■
233% increase (+158koz) from the FY23 Ore Reserve post depletion.
■
Contribution from the maiden South Junction Ore Reserve of 2.6Mt @ 2.7g/t Au
for 225koz.
Updated Bluebird – South Junction Mineral Resource exceeds Interim Mineral
Resource announced in March 2024 by a further 130koz post depletion of 14koz
■
61% increase in Indicated Resources.
■
Ore Reserve underwritten by updated Mineral Resource Estimate (MRE) of 11Mt @
2.8g/t Au for 960koz featuring a Measured and Indicated component of 4.7Mt @
3.1g/t Au for 465koz Au.
Further Resource conversion targeted with substantial drilling program ongoing
■
2 x surface rigs and 2 x underground drill rigs continue to extend and infill the
Bluebird – South Junction Mineral Resource.
■
South Junction remains open at depth and to the south along strike/down plunge.
Production from South Junction to commence in August
■
The significant width of the South Junction orebody enables a highly productive
primary / secondary transverse stoping method which will significantly increase
production from the Bluebird – South Junction system.
■
Production rate of 1.2Mtpa – from Bluebird-South Junction targeted from Q3 FY25.
Westgold Resources Limited
ABN 60 009 260 306
ASX:WGX | TSX:WGX | OTC:WGXRF
westgold.com.au
T: +61 8 9462 3400
E: perth.reception@westgold.com.au
Level 6, 200 St Georges Terrace
Perth WA 6000
PO Box 7068, Cloisters Square WA 6850
Westgold Managing Director and CEO Wayne Bramwell commented:
“Westgold is rapidly building a mine of significant scale and life at Meekatharra. The maiden Ore
Reserve for South Junction and the rapid expansion of the Bluebird-South Junction mining
complex to a 1.2Mtpa run rate by Q3, FY25 has been a remarkable success story and underpins
the value in drilling.
A larger, more productive Bluebird-South Junction underground mine is a game changer for our
Murchison business. It will reduce the requirement and cost of road haulage of ore from Cue
(circa 140km) as the Bluebird-South Junction complex is within 2km of the nearby Bluebird mill.
Westgold will continue to invest in drilling across our portfolio in FY25. With Bluebird-South
Junction and Big Bell in the Murchison, buttressed by the expanding Beta Hunt in the Goldfields,
we continue to build a diversified platform that can produce more consistent and sustainable
long term cashflows and returns to our shareholders.”
Figure 1 - Bluebird – South Junction underground complex showing footprint of current Ore Reserve
Westgold Declares Maiden South Junction Ore Reserve
16 August 2024
2
South Junction – production online in August, due to lift rates from Q3
FY25
Westgold’s pipeline of organic growth targets is extensive. South Junction at Meekatharra was
identified as a priority growth opportunity following the results of initial drill testing of the project
in early 20231. A significant drilling program was initiated in January 2024 aimed at extending and
infilling South Junction. This program continues, with two rigs active on surface and two in the
underground environment.
Westgold recognised the vast scale of South Junction, prompting the undertaking of an interim
MRE2 to expedite mine planning studies. Since March, drilling to increase the confidence in the
Inferred portion of the MRE has progressed in parallel with mine planning studies. The results of
this drilling have enabled Westgold to undertake an update to the MRE that has seen the
substantial conversion of Inferred material to Indicated (See Table 1 and Figure 2). This update
includes 14koz of depletion from three months of production on the Bluebird side of the mine.
Interim March 2024 MRE
Grade
Tonnes
(g/t Au)
Ounces
Tonnes
Measured
302,000
4.4
43,000
304,000
4.1
40,000
Indicated
2,872,000
2.9
264,000
4,368,000
3.0
425,000
Inferred
5,844,000
2.8
520,000
6,032,000
2.6
495,000
Total
9,017,000
2.9
827,000
10,705,000
2.8
960,000
Classification
August 2024 MRE
Grade
(g/t Au)
Ounces
Table 1 – Bluebird - South Junction MRE August 2024 (reported above 1.5g/t Au) 3
Figure 2 – Substantial growth and improvement in MRE quality between Interim and August 2024
1
Refer ASX Release titled “Bluebird Expansion and Drilling Update - 11 January 2023”
2
Refer ASX Release entitled “Bluebird-South Junction Increases to 6.4Mt at 3.1 g/t Au- 16 April 2023”
3
Interim March 2024 MRE as at 31 March 2024 and August 2024 MRE as at 30 June 2024
Westgold Declares Maiden South Junction Ore Reserve
16 August 2024
3
Subsequent mine planning and commercial evaluation works have resulted in an updated Ore
Reserve being declared for the Bluebird – South Junction mine (Table 2). The contribution to this
overall Ore Reserve from the Maiden South Junction Ore Reserve subset is presented in Table 3.
Classification
Proven
Probable
Total
Tonnes
76,600
Grade
(g/t Au)
3.9
Ounces
9,400
2,966,500
2.8
268,000
3,041,000
2.8
277,000
Table 2 – Bluebird - South Junction Ore Reserve August 2024
Classification
Proven
Probable
Total
Grade
(g/t Au)
3.1
Ounces
2,600
2,612,000
2.7
223,000
2,638,000
2.7
226,000
Tonnes
26,300
Table 3 –South Junction Maiden Ore Reserve August 2024
Background to the Ore Reserve Estimation
The South Junction Ore Reserve was estimated using Deswik Shape Optimiser (DSO). These were
run against gradient strings reflective of the potential location for ore drives. The settings used as
part of the DSO run were as follows:
Parameter
Value
Optimisation Field
res_au
Slice Method
YZ
Pillar Between Stopes
0m
Stope Length
5m
Minimum Mining Width
1.2m
Table 4 – DSO Factors
Westgold Declares Maiden South Junction Ore Reserve
16 August 2024
4
Level spacing was mixed and dependent on the gradient strings. As Bluebird and South Junction
orebodies have different geometric characteristics, the level spacing within the two will differ.
Dilution “skins” were not applied to the DSO shapes and instead was completed during the
scheduling stage as these can be continually revised and adjusted during the mining phase.
Although the minimum mining length during the DSO run was set to 5m, it was determined that
the minimum “mineable” stope length is 10m. This was based off the operational likelihood on
mining parameters. Stopes were then created by connecting the 5m shapes into larger stopes
based on the geotechnical parameters. Due to the width of the orebody, a highly productive
primary / secondary transverse stoping method with fill will be employed at South Junction. This
change in method will enable the production rates of Bluebird – South Junction to increase to
more than triple from the current rate of +30kt per month (refer ASX – Westgold March 2024
Quarterly Report) to rates of 100kt per month from Q3 FY25.
Westgold has taken a conservative approach to stope geometry values by keeping the primary
and secondary stope lengths consistent at 17.5m each with the potential to adjust once mining
begins.
Parameter
Value
Minimum stope size length
10m
Maximum stope length
(primary)
Maximum stope length
(secondary)
17.5m
17.5m
Table 5 – Final mining parameters
Modifying factors have been applied to the South Junction Ore Reserve stope shapes that best
reflect the transverse methodology. These have been built from a first principles basis based on
geotechnical recommendations alongside orebody dimensions and geometry.
Parameter
Value
Comments
Mine Operating COG
2.1g/t
Assumes development complete
Full Costed COG
2.3g/t
Incorporates initial and sustaining capital
Stope Recovery
90%
Estimated based on size and dip
Stope Dilution
10%
Calculated based on geotechnical parameters
Development COG
1.0gt
Non-mining costs, assuming material hauled to surface
Table 6 – Modifying factors used for South Junction Ore Reserve
Westgold Declares Maiden South Junction Ore Reserve
16 August 2024
5
Cut-off grades (COG) are based on realised cost profiles determined from the adjacent Bluebird mine
and based on a gold price of $3,000AUD/oz. They have been adjusted to reflect the change in mining
method employed at South Junction.
Processing recoveries used within the mine plan are indicative of those achieved at the Bluebird
plant currently. As Bluebird is an operating mine, environmental, and other governmental
approvals are currently in place.
Figure 3 – Visible gold in recent South Junction drilling
Westgold Declares Maiden South Junction Ore Reserve
16 August 2024
6
Mining in South Junction is scheduled to commence in August
Production rates at South Junction will rapidly increase over the coming months. This ramp up is
a function of the increased scale of the South Junction lodes (as compared to the Bluebird lodes)
which accommodates a more productive mine layout and extraction sequence. (see Figure 4
which depicts the vast difference in scale compared a typical Bluebird stope)
Figure 4 – South Junction schematic mine layout showing the scale of a typical South Junction
stoping panel as compared to a typical stoping panel of the current Bluebird mine (Refer Appendix B
for detailed drill results)
Westgold Declares Maiden South Junction Ore Reserve
16 August 2024
7
Background to the Mineral Resource Estimation
The Yaloginda area which hosts Bluebird – South Junction, is a gold-bearing Archaean greenstone
belt situated ~15km south of Meekatharra. The deposits in the area are hosted in a strained and
metamorphosed volcanic sequence that consists primarily of ultramafic and high-magnesium
basalt with minor komatiite, peridotite, gabbro, tholeiitic basalt and interflow sediments. This
sequence was intruded by a variety of felsic porphyry and intermediate sills and dykes.
South Junction is comprised of numerous mineralised zones broadly located on sub-parallel
north-northeast-trending structures. These zones from west to east are: Edin Hope, South
Junction, Polar Star and Archenar. These zones are offset to the south from the East, Central and
Western lodes at Bluebird. Mining in the Murchison district has occurred since 1800’s providing
significant confidence in the currently geological interpretation of the project.
Geological interpretation of the deposit was carried out using a systematic approach to ensure
that the resultant estimated Mineral Resource figure was both sufficiently constrained, and
representative of the expected sub-surface conditions. In all aspects of Mineral Resource
Estimation, the factual and interpreted geology was used to guide the development of the
interpretation. Geological matrixes were established to assist with interpretation and
construction of the estimation domains. The structural regime is the dominant control on
geological and grade continuity in the Murchison. Lithological factors such as rheology contrast
are secondary controls on grade distribution.
Bluebird – South Junction is mineralised a strike length of >1,800m, a lateral extent of up +50m
and a depth of over 500m.
A significant portion of the data used in resource calculations has been gathered from diamond
core. Multiple sizes have been used. This core is geologically logged and subsequently halved for
sampling. Grade control holes may be whole-cored to streamline the core handling process if
required. Face sampling data is also utilised, where each development face / round is
horizontally chip sampled. The sampling intervals are domained by geological constraints (e.g.
rock type, veining and alteration / sulphidation etc.).
All geology input is logged and validated by the relevant area geologists, incorporated into this is
assessment of sample recovery. No defined relationship exists between sample recovery and
grade, nor has sample bias due to preferential loss or gain of fine or coarse material been noted.
Sampling is analysed by fire assay as outlined below;
■
A representative 40g – 50g sample undergoes fire assay lead collection followed by flame
atomic adsorption spectrometry.
■
Quality control is ensured via the use of standards, blanks and duplicates. The laboratory
includes a minimum of 1 project standard with every 22 samples analysed. No significant
QA/QC issues have arisen in recent drilling results.
After validating the drillhole data to be used in the estimation, interpretation of the mineralsiation
is undertaken in sectional and / or plan view to create the outline strings which form the basis of
the three-dimensional orebody wireframe. Wireframing is then carried out using a combination
of automated stitching algorithms and manual triangulation to create an accurate threedimensional representation of the sub-surface mineralised body.
Westgold Declares Maiden South Junction Ore Reserve
16 August 2024
8
Drillhole intersections within the mineralised body are defined, these intersections are then used
to flag the appropriate sections of the drillhole database tables for compositing purposes.
Drillholes are subsequently composited to allow for grade estimation. In all aspects of resource
estimation, the factual and interpreted geology was used to guide the development of the
interpretation.
Once the sample data has been composited, a statistical analysis is undertaken to assist with
determining estimation search parameters, top-cuts etc. Analysis of individual domains is
undertaken to assist with determining appropriate search parameters. Which are then
incorporated with observed geological and geometrical features to determine the most
appropriate search parameters.
An empty block model is then created for the area of interest. This model contains attributes set
at background values for the various elements of interest as well as density, and various
estimation parameters that are subsequently used to assist in resource categorisation. The
block sizes used in the model will vary depending on orebody geometry, minimum mining units,
estimation parameters and levels of informing data available.
Grade estimation is then undertaken. Ordinary kriging estimation method is considered as
standard, although in some circumstances where sample populations are small, or domains are
unable to be adequately defined, inverse distance weighting estimation techniques will be used.
For very minor lodes, the respective median or average grade is assigned. In these circumstances
lodes are subsequently classified in lower Mineral Resource confidence categories as
appropriate.
Estimation results are validated against primary input data, previous estimates and mining
output.
The Mineral Resource is then depleted for mining voids and subsequently classified in line with
JORC guidelines utilising a combination of various estimation derived parameters and geological
/ mining knowledge.
Data spacing is variable dependent upon the individual lode under consideration. At Bluebird –
South Junction Measured Resources are supported by average drillhole spacing in the range of
15-35m, Indicated from 10-180m and Inferred from 10-200m.
This approach considers all relevant factors and reflects the Competent Person’s view of the
deposit.
The cut off grades used for the reporting of the Mineral Resources have been selected based on
the style of mineralisation, depth from surface of the mineralisation and the most probable
extraction technique and associated costs. At Bluebird – South Junction this has been
determined to be 1.5g/t Au.
Likely mining approaches have been considered at the domaining, estimation and classification
steps. However, no mining dilution or ore loss has been modelled in the resource model or
applied to the reported Mineral Resource. Nor has metallurgical recovery been applied to the
reported Mineral Resource. These factors are applied during the Ore Reserve generation
process.
Westgold Declares Maiden South Junction Ore Reserve
16 August 2024
9
Looking Forward
Westgold’s corporate strategy is to continue to simplify our business by making our biggest
mines bigger and focusing on grade. The expansion of the Bluebird underground to include new
mining fronts from South Junction is consistent with this plan.
Drilling activities continue to expand the Bluebird – South Junction system and increase Mineral
Resource confidence. This continued drilling will ultimately underwrite future updates to the
MRE and Ore Reserve. The orebody remains open at depth and to the south along strike/down
plunge, as can be seen in Figure 1.
Necessary capital projects to enable the larger mine to function effectively are progressively
being scoped and delivered, with power, ventilation and backfill solutions well defined. Westgold
looks forward to providing updates on its progress at Bluebird – South Junction over the coming
months.
Figure 5 – Long Hole rig drilling the first South Junction stope
This announcement is authorised for release to the ASX by the Board.
Investor and media relations enquiries
Investor Relations
Kasun Liyanaarachchi | Investor Relations Manager
investor.relations@westgold.com.au
+61 458 564 483
Westgold Declares Maiden South Junction Ore Reserve
16 August 2024
Media
Peter Knight | Communications Manager
peter.knight@westgold.com.au
+61 459 980 481
10
Competent/Qualified Person Statements
Exploration Results and Mineral Resource Estimates
The information in this release that relates to Exploration results and Mineral Resource Estimates is
compiled by Westgold technical employees and contractors under the supervision of Mr. Jake Russell
B.Sc. (Hons), who is a member of the Australian Institute of Geoscientists and who has verified, reviewed
and approved such information. Mr Russell is a full-time employee of the Company and has sufficient
experience which is relevant to the styles of mineralisation and types of deposit under consideration and
to the activities which he is undertaking to qualify as a Competent Person as defined in the 2012 Edition of
the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (the
“JORC Code”) and as a Qualified Person as defined in the CIM Guidelines and National Instrument 43-101
– Standards of Disclosure for Mineral Projects (“NI 43-101”). Mr. Russell is an employee of the Company
and, accordingly, is not independent for purposes of NI 43-101. Mr Russell consents to and approves the
inclusion in this release of the matters based on his information in the form and context in which it appears.
Mr Russell is eligible to participate in short- and long-term incentive plans of the company.
The updated MRE has an effective date of 30 June 2024 and was completed by Westgold technical
employees and contractors under the supervision of Mr Jake Russell. The key inputs and assumptions are
provided in Appendix C to this release including Section 1 – Sampling Techniques and Data, Section 2 –
Reporting of Exploration Results, Section 3 – Estimation and Reporting of Mineral Resources and Section
4 – Estimation and Reporting of Ore Reserves.
Ore Reserves
The information in this release that relates to Ore Reserve is based on information compiled by Mr. Leigh
Devlin B.Eng. FAusIMM, who has verified, reviewed and approved such information. Mr. Devlin has
sufficient experience which is relevant to the styles of mineralisation and types of deposit under
consideration and to the activities which they are undertaking to qualify as a Competent Person as defined
in the JORC Code and as a Qualified Person as defined in the CIM Guidelines and NI 43-101. Mr. Devlin is
an employee of the Company and, accordingly, is not independent for purposes of NI 43-101. Mr. Devlin
consents to and approves the inclusion in this release of the matters based on his information in the form
and context in which it appears. Mr. Devlin is a full-time senior executive of the Company and is eligible to
and may participate in short-term and long-term incentive plans of the Company as disclosed in its annual
reports and disclosure documents.
General
Mineral Resources, Ore Reserve Estimates and Exploration Targets and Results are calculated in
accordance with the JORC Code. The other technical and scientific information in this release has been
prepared in accordance with the Canadian regulatory requirements set out in NI 43-101 and has been
reviewed on behalf of the company by Qualified Persons, as set forth above.
This release contains references to estimates of Mineral Resources and Ore Reserves. The estimation of
Mineral Resources is inherently uncertain and involves subjective judgments about many relevant
factors. Mineral Resources that are not Ore Reserves do not have demonstrated economic viability. The
accuracy of any such estimates is a function of the quantity and quality of available data, and of the
assumptions made and judgments used in engineering and geological interpretation, which may prove
to be unreliable and depend, to a certain extent, upon the analysis of drilling results and statistical
inferences that may ultimately prove to be inaccurate. Mineral Resource estimates may require reestimation based on, among other things: (i) fluctuations in the price of gold; (ii) results of drilling; (iii)
Westgold Declares Maiden South Junction Ore Reserve
16 August 2024
11
results of metallurgical testing, process and other studies; (iv) changes to proposed mine plans; (v) the
evaluation of mine plans subsequent to the date of any estimates; and (vi) the possible failure to receive
required permits, approvals and licenses.
The NI 43-101 technical report supporting the Maiden Ore Reserve contained in this release will be filed
on SEDAR+ within the next 45 days of the date of this release. Reference should be made to the full text
of the technical report for the assumptions, qualifications and limitations relating thereto.
Forward looking statements
These materials prepared by Westgold Resources Limited include forward looking statements. Often,
but not always, forward looking statements can generally be identified by the use of forward looking
words such as “may”, “will”, “expect”, “intend”, “believe”, “forecast”, “predict”, “plan”, “estimate”,
“anticipate”, “continue”, and “guidance”, or other similar words and may include, without limitation,
statements regarding plans, strategies and objectives of management, anticipated production or
construction commencement dates and expected costs or production outputs.
Forward looking statements inherently involve known and unknown risks, uncertainties and other factors
that may cause the Company’s actual results, performance and achievements to differ materially from
any future results, performance or achievements. Relevant factors may include, but are not limited to,
changes in commodity prices, foreign exchange fluctuations and general economic conditions,
increased costs and demand for production inputs, the speculative nature of exploration and project
development, including the risks of obtaining necessary licenses and permits and diminishing quantities
or grades of reserves, political and social risks, changes to the regulatory framework within which the
Company operates or may in the future operate, environmental conditions including extreme weather
conditions, recruitment and retention of personnel, industrial relations issues and litigation.
Forward looking statements are based on the Company and its management’s good faith assumptions
relating to the financial, market, regulatory and other relevant environments that will exist and affect the
Company’s business and operations in the future. The Company does not give any assurance that the
assumptions on which forward looking statements are based will prove to be correct, or that the
Company’s business or operations will not be affected in any material manner by these or other factors
not foreseen or foreseeable by the Company or management or beyond the Company’s control.
Although the Company attempts and has attempted to identify factors that would cause actual actions,
events or results to differ materially from those disclosed in forward looking statements, there may be
other factors that could cause actual results, performance, achievements or events not to be as
anticipated, estimated or intended, and many events are beyond the reasonable control of the Company.
In addition, the Company’s actual results could differ materially from those anticipated in these forward
looking statements as a result of the factors outlined in the “Risk Factors” section of the Company’s
continuous disclosure filings available on SEDAR+ or the ASX, including, in the Company’s current
annual report, half year report or most recent management discussion and analysis.
Accordingly, readers are cautioned not to place undue reliance on forward looking statements. Forward
looking statements in these materials speak only at the date of issue. Subject to any continuing
obligations under applicable law or any relevant stock exchange listing rules, in providing this
information the Company does not undertake any obligation to publicly update or revise any of the
forward-looking statements or to advise of any change in events, conditions or circumstances.
Westgold Declares Maiden South Junction Ore Reserve
16 August 2024
12
Appendix A
History of South Junction
Mineralisation was discovered at South Junction in mid-1989 by St Barbara Mining. South
Junction was subsequently mined as an open pit from June 1990 through to the early 2000’s.
Total gold production for the open pit phase of operation at South Junction was in excess of
400,000 ounces. However, since open pit mining concluded activity at South Junction has
effectively been dormant.
To the immediate north of South Junction, the Bluebird deposit has been mined at various stages.
This mining was dominated by small scale underground mining operations and open pits until
the turn of the century after which St Barbara, Mercator Gold and Reed Resources mined 485,000
ounces between 2000 – 2013 via substantial open pit operations.
Figure 6 – Yaloginda gold camp is absent deep drilling outside of Bluebird – South Junction
In late 2019, Westgold commenced underground operations at Bluebird which subsequently
produced over 137koz of gold. This brings the total recorded Bluebird production to 784koz and
the combined Bluebird – South Junction production to 1.18Moz. Combining this with the Mineral
Resource remaining, Bluebird – South Junction can be considered a +2Moz system.
Westgold Declares Maiden South Junction Ore Reserve
16 August 2024
13
Murchison Overview
Westgold’s Murchison Operations incorporates four underground mines, three processing
plants and the Great Fingall development project near Cue. Westgold’s Bluebird processing hub
is the largest of our three Murchison processing hubs and is located approximately 15km
southwest of Meekatharra (see Figure 7).
The Bluebird underground mine is the primary ore source feeding the 1.4-1.8Mtpa Bluebird
processing plant. Surface stockpiles and supplementary ore from Cue is trucked to Bluebird to
maintain processing throughputs, with these volumes reducing as the Bluebird-South Junction
mine expands.
Figure 7 – Westgold’s Murchison Asset Map
Westgold Declares Maiden South Junction Ore Reserve
16 August 2024
14
APPENDIX B – Drill Results Included In This Release4
Hole
24BLDD064
24BLDD066
Azi
7,043,673
-47
101
-53
113
7,043,673
641,491
641,491
100
100
3.07m at 2.30g/t Au
15
1m at 6.37g/t Au
41
31.37m at 5.55g/t Au
122
15.5m at 4.62g/t Au
158
4.6m at 3.79g/t Au
21
22.8m at 1.25g/t Au
173
15.82m at 3.09g/t Au
210
18.9m at 3.65g/t Au
293
24BLDD095
7,043,757
641,489
96
9.25m at 3.79g/t Au
122
-22
67
24SJDD001
7043454
641917
468
10.45m at 3.80g/t Au
788
-79
302
3.98m at 10.80g/t Au
894.49
3.75m at 3.01g/t Au
560
-48
292
9.45m at 2.54g/t Au
573.85
3.29m at 3.28g/t Au
588.53
12.70m at 8.57g/t Au
415.58
-53
296
8.03m at 1.58g/t Au
543.44
-52
296
-59
293
-59
284
-65
294
24SJDD004
24SJDD010
24SJDD012
24SJDD015
24SJDD019_W1
24SJDD021_W2
4
Collar N Collar E Collar RL Intercept (Downhole) From (m) Dip
7043417
7043417
7043411
7043411
7043410
7043405
641924
641925
641923
641923
641925
641939
468
467
467
467
4.00m at 3.81g/t Au
637
2.00m at 6.72g/t Au
418
7.90m at 5.20g/t Au
592.5
6.80m at 3.87g/t Au
600.9
3.68m at 4.55g/t Au
619.87
3.00m at 4.54g/t Au
482
3.00m at 12.91g/t Au
531.7
8.10m at 4.31g/t Au
656
2.21m at 17.30g/t Au
696.79
6.27m at 3.76g/t Au
641.42
2.62m at 4.26g/t Au
648.53
5.79m at 2.39g/t Au
541.71
4.70m at 4.58g/t Au
550.3
20.94m at 6.74g/t Au
681.86
INC 4.68m at 16.48g/t Au
687
467
467
Refer to Westgold’s Q2 FY24, Q3 FY24 and Q4 FY24 Quarterly Reports on ASX for full South Junction drill results
Westgold Declares Maiden South Junction Ore Reserve
16 August 2024
15
APPENDIX C – JORC 2012 TABLE 1 – GOLD DIVISION
SECTION 1: SAMPLING TECHNIQUES AND DATA
(Criteria in this section apply to all succeeding sections.)
Criteria
Sampling techniques
JORC Code Explanation
Commentary
•
•
•
•
•
Drilling techniques
•
Nature and quality of sampling (e.g. cut channels, random chips, or
specific specialised industry standard measurement tools
appropriate to the minerals under investigation, such as down hole
gamma sondes, or handheld XRF instruments, etc.). These
examples should not be taken as limiting the broad meaning of
samplin