September 2024 Quarterly Results
Released
Released
Announcement PDF
September 2024 Quarterly Report
31 October 2024
ASX Release
Westgold is an agile
Australian gold company.
$1.4B merger lifts Westgold into ASX 200
ASX200
With six operating mines and
combined processing capacity of
~7Mtpa across two of Western
Australia’s most prolific gold regions –
we have a clear vision and strategy to
sustainably produce +500,000 ozpa
from FY26/27.
Perth, Western Australia, 31 October 2024 Westgold
Resources Limited (ASX: WGX, ASX:TSX, OTCQX: WGXRF Westgold or the Company) is pleased to report results for the
period ending 30 September 2024 (Q1 FY25).
HIGHLIGHTS
OPERATIONS
Safety Performance Total Recordable Injury Frequency
Rate (TRIFR) of 7.37 / million hours – an increase of ~8% as
we integrate the Southern Goldfields Operations
Q1 FY25 record gold production post Karora merger
77,369oz Au @ AISC of $2,422/oz during a transitional
quarter including only 2 months Southern Goldfields
production
On Track for FY25 Guidance 400,000 to 420,000 ozpa @
AISC of $2,000 - $2,300 with ramp-up back ended in H2 FY25
EXPLORATION & RESOURCE DEVELOPMENT
Seventeen drill rigs operating across portfolio
Bluebird – South Junction Ore Reserve increased by 233%
to 3.0Mt @ 2.8g/t Au for 277koz
Updated Group Mineral Resource Estimate (+60% to
13.2Moz Au) and Ore Reserve (+69% to 3.3Moz Au)
Impressive drill results from both the Murchison and
Southern Goldfields:
This announcement is authorised for
release to the ASX by the Board.
Investor Relations
Annette Ellis | IR Manager
investor.relations@westgold.com.au
+61 458 200 039
Media
Peter Knight | Communications Manager
peter.knight@westgold.com.au
+61 459 980 481
Westgold Resources Limited
ASX: WGX | TSX: WGX | OTC: WGXRF
ABN 60 009 260 306
■
19.00m @ 13.44g/t Au from 24SJDD028 at South Junction
(See ASX Announcement of 5 September 2024)
■
4.00m @ 22.45g/t Au in hole WF440N1-01AR at Beta
Hunt Fletcher Zone (See ASX Announcement of 21 August
2024)
CORPORATE
$1.4B Merger completed - Westgold listed on TSX and rejoins
S&P/ASX 200
Closing cash, bullion, and liquid investments at 30 September
of $103M and undrawn $100M Revolving Corporate Facility
Final Dividend declared 1.25 cent per share fully franked
Westgold remains 100% unhedged – offering full exposure to
escalating gold price
westgold.com.au
T: +61 8 9462 3400
E: perth.reception@westgold.com.au
Level 6, 200 St Georges Terrace
Perth WA 6000 / PO Box 7068
Cloisters Square WA 6850
Westgold Managing Director and CEO Wayne Bramwell commented:
“Q1 FY25 represents both a transformational and a transitional period for Westgold.
On 1 August Westgold completed a $1.4B merger with Karora Resources that has transformed Westgold
into a 400,000+ ozpa, top five Australian gold producer. On 6 August we commenced trading on the Toronto
Stock Exchange and in September, Westgold joined the ranks of S&P’s ASX200.
Six quarters of disciplined and sustained cash-build from our Murchison operations delivered free cash
and drove the value in Westgold’s scrip that allowed us to complete the merger without a capital raise or
debt draw down debt. Importantly at the end of the quarter, Westgold remained unhedged and debt free,
with its $100M Revolving Corporate Facility undrawn.
The operating results for this quarter mark a transition in scale for Westgold and include three months of
gold production from the Murchison operations, but only two months’ production from the Southern
Goldfields. The expanded business delivered a record 77,369 ounces (~90koz normalised for a full quarter
of Southern Goldfields production) at an AISC of $2,422/oz, generating $29M in net mine cashflow.
Our focus post-merger has been to rapidly identify, then address key risks and opportunities across the
Southern Goldfields operations. Early activities include deploying additional safety and operational
management to supplement the site teams and expedite remedial maintenance and upgrades in basic
mine infrastructure (water, ventilation, power). These changes have had immediate positive impact on
mine outputs at both Beta Hunt and Higginsville late in the quarter and will see productivity improve as
each area is addressed.
Integration across the business continues and importantly, Westgold remains on track to meet our FY25
guidance. Production and cost guidance is geared to the second half of the year as Bluebird South-Junction
ramps up to a run rate of more than 1Mtpa, Beta Hunt delivers consistent output of more than 2Mtpa run
rate and mining commences at Great Fingall.
Westgold now has an extensive, pipeline of projects with a landholding of more than 3,200km2 across two
of Australia’s most prolific gold regions. Drilling will unlock value and as planned we have rapidly mobilised
additional drills to Beta Hunt and prioritised targets across Higginsville.
The 100 day integration plan will be complete during Q2 FY25 and we are confident in higher mine outputs
and reduced costs across the business as these programmes are systematically rolled out and synergies
delivered.”
ENDS
September 2024 Quarterly Report
2
Executive Summary
Cash Position at 30 September 2024
Westgold closed the quarter with cash, bullion and liquid investments of $103M (see Figure 1). Notably, this
result was net of the significant cash component and major once-off costs relating to the Company’s $1.4B
merger with TSX listed Karora Resources Inc (Karora) during the period.
Costs relating to the transaction include $125M cash payment to Karora shareholders, $28M in change of
control payments to Karora’s directors, executives and advisor fees.
400
82
350
300
250
$'m
32
263
19
200
21
(17)
(34)
268
(20)
(13) (2)
8
37
(64)
(12)
11
208
150
100
(153)
103
Closing Cash, Bullion
and Liquid Investments
Merger Costs
Closing Investments
Closing Bullion
Closing Cash pre merger costs
Lease Payments
Working Capital
Inventories - stockpiles
Exploration
PP&E
Growth Capital
Sustaining Capital
Southern Goldfields Op C/Flow
Murchison Op C/Flow
Opening Cash
Opening KRR Cash
Opening Investments
Opening Bullion
-
Murchison Opening Cash, Bullion
and Liquid Investments
50
Figure 1: Cash, Bullion, and Liquid Investments Movement – Q1 FY25
Notes
•
•
Cash acquired of $32M from Karora on 1 August is net of the Macquarie debt repayment of $44M and Culico Metals and
Kali Metals contributions of $11M.
Operating Cash Flows includes:
Southern Goldfields for August and September only
Merger Costs of $153M relates to:
o
$125M cash consideration paid to Karora Resources shareholders,
o
$7M to advisors’ costs (legal, financial, taxation and corporate advisory).
o
$21M change of control payments to Karora’s Executives and Directors,
September 2024 Quarterly Report
3
Group Production Highlights – Q1 FY25
Westgold produced 77,369 ounces of gold in Q1 FY25, its highest quarterly gold production yet, returning net
mine cashflow of $29M. This result was from three months of production from the Murchison (52,889 ounces)
but only two months of production from the Southern Goldfields operations (24,480 ounces).
All-In Sustaining Cost (AISC) for the quarter was $2,422/oz (Q4 FY24 $2,041/oz).
The elevated costs in Q1 FY25 reflect the transitional nature of the quarter. In the Southern Goldfields
production was impacted by the poor performance of the Pioneer Open Pit at Higginsville and lower than
expected ounce production from Beta Hunt.
Capital growth projects continued to advance across the Group whilst the Fender underground at Cue
transitioned to commercial production during the quarter.
Gold production (oz)
Figure 2: Westgold Quarterly Production (oz), Achieved Gold Price and AISC ($/oz)
September 2024 Quarterly Report
4
Figure 3: Westgold Monthly AISC
The Company sold 72,202 oz of gold for the quarter achieving a record price of $3,723/oz, generating $269M in
revenue. With Westgold free of any fixed forward sales contracts, the Company continues to offer shareholders
full exposure to record spot gold prices.
Westgold’s operations generated $101M of mine operating cashflows with the achieved gold price $1,301/oz
over AISC. AISC for Q1 FY25 of $187M (Q4 FY24 of $108M) was impacted by $65M in additional costs from
the Southern Goldfields and Fender transitioning to commercial production.
Capital expenditure during Q1 FY25 of $58M (Q4 FY24 $64M) includes $39M investment in growth projects
(Bluebird-South Junction and Big Bell expansions and the Great Fingall development), and upgrading
processing facilities and infrastructure.
Investment in exploration and resource development of $14M for the quarter was focussed on Bluebird-South
Junction and Starlight in the Murchison, and the Fletcher Zone and Two Boys underground in the Southern
Goldfields.
The net mine cash inflow for Q1 FY25 was $29M (refer Table 1 under Group Performance Metrics).
September 2024 Quarterly Report
5
Environmental, Social and Governance (ESG)
People
During the quarter female participation in the workforce increased from 12.5% to 14.6%. Family and medical
leave guidelines were rolled out to the wider business, with a pleasing increase in men utilising paternal leave
as either the primary or secondary carer.
Staff retention continued to improve, with record low turnover.
At the end of the quarter, Westgold employed 2,100 employees and contractors. Integration of the Southern
Goldfields was a major focus as policies, procedures and processes were aligned.
Safety, Health, the Environment and Community
Westgold’s Murchison business achieved a 16.44% reduction in its key safety metric for the full FY24 financial
year. With the integration of the Southern Goldfields assets, the Total Recordable Injury Frequency Rate (TRIFR)
increased to 7.37 injuries per million hours worked, representing an increase of 7.59% quarter on quarter.
The business incurred two Lost Time Injuries, increasing the Lost Time Injury Frequency Rate (LTIFR) by 61.29%
to 1.00. The High Potential Incident frequency decreased by 24.17% to 5.18. Significant Psychosocial Harm
Events remains at 0.00.
One Significant Environmental Incident was recorded during the quarter with a pipeline break at the Higginsville
processing facility resulting in a tailings spill. The spill was reported to the regulator and immediately
remediated to minimise environmental impact.
Figure 4: Southern Goldfields integration led to a rise in TRIFR during Q1 FY25
September 2024 Quarterly Report
6
Group Performance Metrics
Westgold’s quarterly physical and financial outputs for Q1 FY25 are summarised below. The Group operates
across the Murchison and Southern Goldfields regions of Western Australia with the Murchison Operations
incorporating four underground mines (Bluebird-South Junction, Starlight, Big Bell, and Fender) and three
processing hubs (Fortnum, Tuckabianna and Bluebird).
Westgold’s merger with Karora Resources completed on 1 August 2024. The Karora assets are grouped and
reported as Westgold’s Southern Goldfields operations – incorporating the Beta Hunt and Two Boys
underground mines (Pioneer open pit closed in September) and two processing hubs (Higginsville and
Lakewood).
Table 1: Westgold Q1 FY25 Performance
650,066
Southern
Goldfields
291,442
941,508
g/t
2.4
2.3
2.4
ROM - OP Ore Mined
t
-
70,388
70,388
OP Grade Mined
g/t
-
2.1
2.1
Ore Processed
t
878,890
410,671
1,289,561
Head Grade
g/t
2.1
2.0
2.1
Recovery
%
90
92
90
Gold Produced
oz
52,889
24,480
77,369
Gold Sold
oz
49,813
22,389
72,202
A$/oz
3,723
3,723
3,723
Mining
A$’M
57
31
88
Processing
A$’M
32
21
53
Admin
A$’M
7
5
11
Stockpile Movements
A$’M
1
(2)
(2)
Royalties
A$’M
5
5
10
Cash Cost (produced oz)
A$’M
101
60
161
Corporate Costs
A$’M
3
1
4
Sustaining Capital
A$’M
17
5
23
All-in Sustaining Costs
A$’M
121
65
187
All-in Sustaining Costs
A$/oz
2,294
2,696
2,422
Physical Summary
Units
Murchison
ROM - UG Ore Mined
t
UG Grade Mined
Achieved Gold Price
Group
Cost Summary
September 2024 Quarterly Report
7
Units
Murchison
Southern
Goldfields
Group
Notional Revenue (produced oz)
A$’M
197
91
288
All-in Sustaining Costs
A$’M
(121)
(65)
(187)
Mine Operating Cashflow
A$’M
76
26
101
Growth Capital
A$’M
(34)
(5)
(39)
Plant and Equipment
A$’M
(11)
(8)
(19)
Exploration Spend
A$’M
(11)
(3)
(14)
Net Mine Cashflow
A$’M
20
9
29
Net Mine Cashflow
A$/oz
369
367
368
Physical Summary
Notional Cashflow Summary
Q1 FY25 Group Performance Overview
Westgold processed 1,289,561t (Q4 FY24 – 862,889t) of ore in total at an average grade of 2.1g/t Au (Q4 FY24
– 2.1g/t Au), producing 77,369oz of gold (Q4 FY24 – 52,795oz). Group AISC in Q1 FY25 was $187M (Q4 FY24 $108M). The $79M increase reflects the enlarged Westgold post-merger (Southern Goldfields $66M).
MURCHISON
Mining costs in the Murchison were $1,074/oz (Q4 FY25 $817/oz) coinciding with the Fender mine achieving
commercial production on 1 July 2024.
Ore stockpiles built-up during Q4 FY24 as a result of atypical rainfall in the Murchison were processed in
Q1 FY25. As Bluebird-South Junction ramps up from 500kt to >1Mtpa during the year, the current reliance on
hauling comparatively lower-grade, stockpiled ore from Fortnum and Cue will reduce accordingly, improving
both economic performance and gold production from the Murchison operations.
The Bluebird mill commenced planned maintenance on crushing and milling circuits in September to prepare
the processing hub for higher throughputs and increased delivery of higher grade ore from an expanded
Bluebird-South Junction in H2 FY25.
Total Capital expenditure of $45M, included Growth Capital ($34M) and Plant and Equipment ($11M) across
the Murchison operations. Growth Capital related to planned expansions at Big Bell, Great Fingall
development, Bluebird – South Junction and Starlight mine sites. Plant and Equipment capital related to
Processing facilities ($5M), Paste plant ($5M) and Camp upgrades ($1M) during the quarter.
September 2024 Quarterly Report
8
SOUTHERN GOLDFIELDS
Equipment, personnel availability, power, water and ventilation issues combined to impact mine production
performance at Beta Hunt and Two Boys in August. These issues are being systematically addressed with
operational outputs beginning to improve from October.
The Pioneer open pit at Higginsville ceased operations during the quarter. An estimated 1,000oz from the pit
was unable to be recovered following failure of the eastern wall immediately following the final blast, impacting
revenue for the quarter.
Total Capital Expenditure of $13M, included Growth Capital ($5M) and Plant and Equipment ($8M) across the
Southern Goldfields operations relating to Beta Hunt mine, processing facilities and underground equipment.
Table 2: Q1 FY25 Group Mining Physicals
Murchison
Ore Mined
(‘000 t)
Mined Grade
(g/t)
Contained ounces
(Oz)
Bluebird
95
3.71
11,297
Fender
75
2.45
5,851
Big Bell
307
1.94
19,143
Starlight
174
2.67
14,936
Southern Goldfields
Ore Mined
(‘000 t)
Mined Grade
(g/t)
Contained ounces
(Oz)
Beta Hunt
250
2.36
18,949
Two Boys
42
2.58
3,464
Pioneer OP
70
2.12
4,786
GROUP
1,012
2.41
78,427
September 2024 Quarterly Report
9
Table 3: Q1 FY25 Group Processing Physicals
1
Murchison
Ore Milled
(‘000 t)
Head Grade
(g/t)
Recovery
(%)
Gold Production
(Oz)
Bluebird
91
3.74
93
10,149
Fender
87
2.36
86
5,677
Open Pit & Low Grade 1
171
0.95
86
4,480
Bluebird Hub
349
2.03
89
20,306
Big Bell
311
1.94
88
16,998
Open Pit & Low Grade
23
0.81
87
516
Tuckabianna Hub
334
1.86
87
17,514
Starlight
165
2.81
95
14,155
Open Pit & Low Grade
31
0.97
95
914
Fortnum Hub
196
2.52
95
15,069
Southern Operations
Ore Milled
(‘000 t)
Head Grade
(g/t)
Recovery
(%)
Q4 Gold Production
(Oz)
Beta Hunt
202
2.31
92
13,893
Lakewood Hub
202
2.31
92
13,893
Beta Hunt
32
2.16
94
2,096
Two Boys
35
2.55
91
2,593
Pioneer OP
74
1.99
91
4,320
Open Pit & Low Grade
68
0.81
89
1,578
Higginsville Hub
209
1.73
92
10,587
GROUP TOTAL
1,290
2.06
90
77,369
Includes low grade ore mined at Big Bell and trucked to Bluebird
September 2024 Quarterly Report
10
Operations Summary
Murchison
Figure 5: Murchison Location Map
September 2024 Quarterly Report
11
■
Bluebird – South Junction Underground Mine (Meekatharra)
The first South Junction stope was successfully fired in August, with stopes on PHO_1095 and BLU_1065
levels mined during the quarter. Production ramp up slowed temporarily due to equipment availability
and resourcing issues, however these were resolved by the end of the quarter, with the stoping sequence
re-established and production resuming at the planned rates.
Orders have been placed for additional mobile equipment to support the ramp up of production into H2
FY25, and the focus remains on the South Junction Decline and advancing to the next production
SOU_1036 level to expand Bluebird’s production to a run rate of 1.2Mtpa in the second half of the
financial year.
The Bluebird-South Junction mining complex is growing with the current expansion of mine outputs
driven by the commencement of mining the South Junction lodes. This expansion has required
investment into an upgrade in the primary ventilation system, the introduction of paste fill for full
resource extraction and additional mobile equipment. Larger tonnages per vertical metre of advance will
significantly improve the capital intensity of the mine once the initial capital investment phase has been
completed.
■
Bluebird Mill (Meekatharra)
The Bluebird-South Junction and Fender underground mines were primary sources of ore feed to the
Bluebird processing hub. Plant throughput of ~349,000t was slightly lower (-5%) compared to the
previous quarter due to planned maintenance. Work was carried out on crushing and milling
components in preparation for the ramp up and higher tonnages of higher-grade ore from Bluebird –
South Junction underground operations.
The works undertaken will increase the availability and reliability of the plant as ore production from
Bluebird South-Junction ramps up from 500ktpa to a run rate of 1.2Mtpa in H2 FY25.
■
Fender Underground Mine (Cue)
Production was steady throughout the quarter averaging 25kt per month and outperforming the project’s
Ore Reserve in terms of ounces by 16%. Improvement in output was the result of focus on mine
production efficiency and maintaining multiple stopes online. Fender continues to take advantage of
synergies with Big Bell to ensure production forecast is achieved.
Westgold expects this trend to continue into the coming quarter as the remainder of the 175 level stopes
are extracted. Accelerating the decline to bring online an additional production level on the 205L was
also a priority during the reporting period.
■
Big Bell Underground Mine (Cue)
Production from the cave was steady throughout the quarter averaging 102kt per month. High grade
drawpoints in the 685S and 710N levels resulted in an improvement of mine grade from the previous
quarter. Changes to the operating strategy have delivered an improvement in underground equipment
availability and steadied production.
September 2024 Quarterly Report
12
■
Tuckabianna Processing Hub (Cue)
Big Bell underground ore was the primary source of ore feed to the Tuckabianna processing hub.
Throughput increase by 7% compared to the previous quarter due to a consistent ore blend from Big Bell.
Recovery was 88.7%. This is the highest it has been since Sept 2022, as a result of maintaining consistent
mill operating parameters.
Construction of the Tuckabianna West in-pit tailing storage facility is progressing to plan, with
earthworks, piping, and power lines complete.
■
Starlight Underground Mine (Fortnum)
Production increased by 16% compared to the previous quarter due to multiple work areas available in
the Starlight and Nightfall lodes. Nightfall continues delivering strong production results with stopes on
NF 1160 level exceeding planned mine grades. Development continues to accelerate with the top down
and bottom-up access to the Nightfall area.
Mining scale studies have also commenced at Starlight, with modelling and evaluation of differing
endowment and production points along the continuum between selective mining and more
comprehensive resource extraction. This work is expected to progress over the coming quarters. In
addition, to support the outcome of this evaluation, ventilation network expansion and upgrade studies
are currently progressing which will allow for anticipated increased production levels from the mine.
■
Fortnum Processing Hub (Fortnum)
Starlight underground material contributed 90% of the ore feed to the Fortnum processing hub, with the
remaining 10% sourced from low grade stockpiles. Installation of a pebble crusher in July has resulted in
a 3% increase in the mill throughput rate compared to the previous quarter.
■
Great Fingall Underground Mine (Cue)
Great Fingall is currently in development and achieved a record month for development advancement in
August. The decline is tracking well against plan.
Mining evaluations continued on the Great Fingall Flats and other early production opportunities.
Installation of LOM mine infrastructure is progressing to plan, including an upgrade of the dewatering
infrastructure to expediate dewatering of the Great Fingall Reef.
Preparations are underway for the return of an underground diamond drilling rig to the mine. The initial
target of drilling will be the upper extensions to the Golden Crown orebody which is anticipated to present
an additional early production opportunity if assay results are in line with historic performance. The site
team will also take the opportunity to undertake an early test of remnant portions of the Great Fingall
Reef.
Importantly, both of these projects if successfully converted into mining opportunities, will not detract
from the current operational plan which is focused on accessing the high-value Great Fingall Reef
extensions in the shortest possible time. They will be assessed and resourced as additional opportunities
outside of the existing plan.
September 2024 Quarterly Report
13
Southern Goldfields
Figure 6: Southern Goldfields Location Map
■
Beta Hunt Underground Mine (Kambalda)
Q1 FY25 saw two months of Beta Hunt production included within Westgold’s result, with poor mine
productivity in August. Development advanced during the quarter and was nearing completion in AZ 19L,
where coarse gold from the Father’s Day lode was forecast, however, was not mined during the quarter.
Westgold is currently developing a comprehensive infrastructure replacement and upgrade plan to
support the projected increased levels of production from the mine, focussing primarily on electrical,
ventilation and water distribution networks.
September 2024 Quarterly Report
14
Mine productivity began to lift during the quarter as Westgold:
•
supplemented the site operational team with additional safety and production management
resources;
•
implemented surface digital tele-remote bogging, a key element underpinning improving underground
production efficiencies;
•
focussed on truck utilisation – this began to improve post-merger due to synergies of a larger
workforce across the business, this resulted in increased production towards the end of the quarter,
with the full benefits expected to be evidenced quarter on quarter; and
•
commenced upgrading the mine capital infrastructure to support a ramp up to 2.0Mtpa and further
improve mining efficiencies – this included pumping infrastructure, power reticulation and ventilation.
Westgold has lifted the intensity of geological work at Beta Hunt, with two Westgold diamond drill rigs
mobilised to site to complement the four contractor drill rigs currently operating at the mine. The focus
of the Westgold-owned rigs is the Fletcher zone where a Global Exploration Target of 23-27Mt at 2.12.5g/t Au for 1.6-2.1Moz. has been defined (refer ASX 16 September 2024 - Fletcher Exploration Target
Defined at 1.6 - 2.1Moz Au).
Work is currently underway to integrate disparate areas of the Beta Hunt mine into a single geological
structural and resource framework. This will allow more comprehensive mining evaluations and
planning, to inform more efficient mining outcomes. The process continues into the coming quarter.
■
Lakewood Processing Hub (Kalgoorlie)
Beta Hunt underground material was the primary ore feed for the 1.2Mtpa Lakewood Mill at Kalgoorlie.
Mill throughput was up 5% against forecasts for the two months of operation under Westgold’s control.
■
Two Boys Underground Mine (Higginsville)
Production at the Two Boys underground mine was steady averaging a monthly production rate of 21kt.
Plans have been finalised to upgrade the primary ventilation system to de-constrain development
activities, with works planned for early Q2.
Initial technical work has focused on extending the life of the Two Boys underground mine beyond its
previously projected end of calendar year closure date. Pleasingly, mining has already been pushed
beyond the boundaries of the previously defined mine plan, with production rates now at sustainable
levels and drill platform development underway to allow for extensional drilling.
■
Pioneer Open Pit (Higginsville)
The completion of the Pioneer pit post-merger was delayed due to a slip on the eastern wall which pushed
out the completion date to late August. All open pit contractors were demobilised in early September.
■
Higginsville Processing Hub (Higginsville)
Operations within the Higginsville hub include a 1.6Mtpa processing plant, the Two Boy underground
mine, and the Pioneer open pit which was closed in September. A tailing storage facility lift is in progress
at Higginsville, to provide additional required storage capacity from Q2, FY25 onwards.
Throughput was slightly lower than planned due to a mill shutdown for a ball mill reline which had been
budgeted in July, however was rescheduled into August due to limited availability of third party
maintenance resources. Following depletion of Pioneer ore stock, ore feed into the mill was
supplemented with the introduction of other lower grade stockpiled ore from September.
September 2024 Quarterly Report
15
Exploration and Resource Development
Westgold continues to invest in exploration and resource development across the Company’s highly
prospective tenement portfolio. Key activities included:
Murchison
RESOURCE DEVELOPMENT ACTIVITIES
Starlight (Fortnum)
Resource drilling continued in the Nightfall Deeps and the Galaxy lode to expand the Starlight resource and
provide further mining optionality. Work at Starlight this quarter has focussed on infilling and extending the
mine plan for the high-grade Nightfall area.
Pleasing results continue to be returned both within and adjacent to the mine plan area, such as:
2m at 51.98g/t Au from 71m in NF875RD04,
3.69m at 21.17g/t Au from 138m in NF900RD02A and
2.59m at 42.2g/t Au from 73m in NF900RD04.
Figure 7: Starlight schematic long-section showing better drill results returned in Q1 FY25.
September 2024 Quarterly Report
16
Bluebird – South Junction (Meekatharra)
Westgold has continued to aggressively drill the Bluebird - South Junction system with multiple drill rigs active
on surface and underground. Assay results continue to be highly encouraging with updates provided through
ASX releases dated 14 May 2024, 2 July 2024 and 5 September 2024. Please refer to these releases for the most
recent drill results.
The continuation of the South Junction drilling program culminated in the declaration of a maiden South
Junction Ore Reserve, with the combined Bluebird - South Junction Ore Reserve now 3.0Mt at 2.8 g/t Au for
277koz (refer ASX 14 August 2024 - Westgold Declares Maiden South Junction Ore Reserve).
The significant width of the South Junction orebody enables a highly productive primary / secondary transverse
stoping method which could significantly increase production from MGO. The Ore Reserve is underwritten by
an updated Mineral Resource Estimate of 11Mt at 2.8g/t for 950koz (refer ASX Announcement on16 April 2024
- Bluebird-South Junction Increases to 6.4Mt at 3.1 g/t Au).
Figure 8: Bluebird-South Junction schematic long-section showing select near mine drill results in Q1 FY25.
September 2024 Quarterly Report
17
Big Bell (Cue)
In the Murchison, resource drilling at Big Bell remains ongoing, and continues to infill zones within the near
term portion of the Longhole Open Stoping mine plan. Results such as:
10m at 7.04g/t Au from 224m in 24BBDD0011,
23.01m at 3.4g/t Au from 221m in 24BBDD0015 and
8m at 11.15g/t Au from 203m in 24BBDD0017
hint at the grade flexibility selective mining of this large system will allow.
Figure 9: Big Bell schematic long-section showing better drill results returned in Q1 FY25.
GREENFIELDS ACTIVITIES
Greenfields activities in the Murchison included 10,686m of aircore (AC) drilling testing early stage targets in
the Nannine (Meekatharra) and Labouchere (Fortnum) regions during August and September with assay results
now starting to be returned with some early encouragement.
These results will be reported in detail in Q2.
Development of various Reverse Circulation (RC) drilling programs to test more advanced targets continued
during the period including for Mountain View (Cue), Champion (Meekatharra) and Peak Hill (Fortnum). Drilling
is planned to commence on these targets towards the end of October 2024.
September 2024 Quarterly Report
18
Southern Goldfields
RESOURCE DEVELOPMENT ACTIVITIES
Beta Hunt (Kambalda)
Drilling of the Fletcher Zone was accelerated during the quarter with the addition of two Westgold owned drill
rigs to complement the existing single contract drill rig. Better results this quarter included 4